Damac Hills - Golf Gate 2 construction photos

58 photos from 9 site inspections, newest first. The percentage is how much of Damac Hills - Golf Gate 2 was built on the day of each visit.

20 July 202680% built

25 March 202660% built

27 November 202543% built

15 August 202530% built

1 May 202520% built

21 January 20257.9% built

20 May 20242.7% built

26 December 20230.1% built

8 June 20230% built

Back to Damac Hills - Golf Gate 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.