Damac Hills - Gems Estates 2 construction photos
49 photos from 9 site inspections, newest first. The percentage is how much of Damac Hills - Gems Estates 2 was built on the day of each visit.
14 April 202663% built
23 October 202562% built
13 May 202553% built
21 January 202531% built
5 July 202422% built
5 December 20238.4% built
10 August 20236.5% built
20 March 20230.5% built
15 September 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.