Damac Hills - Carson construction photos
122 photos from 16 site inspections, newest first. The percentage is how much of Damac Hills - Carson was built on the day of each visit.
29 March 2022100% built
4 August 202198% built
21 December 202090% built
12 May 202081% built
21 October 201976% built
9 May 201962% built
28 November 201841% built
16 July 201831% built
18 March 201822% built
15 November 201721% built
10 July 201718% built
13 April 201713% built
6 December 201611% built
2 August 20166.6% built
22 December 20154.6% built
12 August 20151.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.