140 photos from 17 site inspections, newest first. The percentage is how much of Damac Hills (2) - Zinnia was built on the day of each visit.

2 June 2022100% built

15 September 202197% built

6 July 202191% built

16 December 202082% built

28 May 202076% built

19 December 201970% built

23 June 201960% built

13 February 201958% built

11 September 201857% built

14 February 201853% built

8 October 201751% built

13 August 201747% built

3 July 201745% built

16 January 201729% built

8 August 201614% built

24 February 20164.0% built

11 May 20152.8% built

Back to Damac Hills (2) - Zinnia construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.