Damac Hills (2) - Viridis construction photos

148 photos from 16 site inspections, newest first. The percentage is how much of Damac Hills (2) - Viridis was built on the day of each visit.

3 April 2023100% built

21 September 202299% built

10 February 202299% built

4 July 202194% built

25 January 202189% built

6 July 202075% built

20 November 201971% built

19 June 201964% built

19 February 201960% built

11 October 201843% built

16 May 201831% built

9 January 201820% built

3 July 20177.4% built

17 January 20173.9% built

9 August 20163.1% built

14 March 20162.0% built

Back to Damac Hills (2) - Viridis construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.