Damac Hills (2) - Violet construction photos

52 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Damac Hills (2) - Violet was built on the day of each visit.

30 September 202695% built

14 July 202688% built

14 April 202685% built

13 October 202570% built

28 May 202555% built

27 December 202436% built

17 April 20243.6% built

31 July 20230% built

Back to Damac Hills (2) - Violet construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.