Damac Hills (2) - Victoria construction photos
88 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills (2) - Victoria was built on the day of each visit.
25 August 2022100% built
7 February 202295% built
5 August 202191% built
28 January 202170% built
6 July 202045% built
25 February 202027% built
28 October 201912% built
12 June 20195.6% built
9 January 20193.3% built
9 January 20182.3% built
21 August 20171.8% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.