Damac Hills (2) - Sycamore construction photos

129 photos from 16 site inspections, newest first. The percentage is how much of Damac Hills (2) - Sycamore was built on the day of each visit.

26 August 2021100% built

14 April 2021100% built

16 December 202097% built

28 May 202081% built

19 December 201970% built

23 June 201963% built

13 February 201960% built

11 September 201858% built

14 February 201854% built

8 October 201751% built

13 August 201749% built

3 July 201747% built

16 January 201728% built

8 August 201612% built

24 February 20165.1% built

11 May 20152.3% built

Back to Damac Hills (2) - Sycamore construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.