Damac Hills (2) - Primrose construction photos
104 photos from 15 site inspections, newest first. The percentage is how much of Damac Hills (2) - Primrose was built on the day of each visit.
10 February 2021100% built
1 June 202099% built
18 December 201998% built
19 June 201992% built
20 January 201982% built
9 October 201875% built
11 June 201868% built
14 February 201858% built
8 October 201755% built
13 August 201750% built
3 July 201746% built
17 January 201724% built
9 August 20165.2% built
11 November 20152.8% built
25 February 20152.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.