Damac Hills (2) - Primrose construction photos

104 photos from 15 site inspections, newest first. The percentage is how much of Damac Hills (2) - Primrose was built on the day of each visit.

10 February 2021100% built

1 June 202099% built

18 December 201998% built

19 June 201992% built

20 January 201982% built

9 October 201875% built

11 June 201868% built

14 February 201858% built

8 October 201755% built

13 August 201750% built

3 July 201746% built

17 January 201724% built

9 August 20165.2% built

11 November 20152.8% built

25 February 20152.1% built

Back to Damac Hills (2) - Primrose construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.