Damac Hills (2) - Navitas construction photos
89 photos from 13 site inspections, newest first. The percentage is how much of Damac Hills (2) - Navitas was built on the day of each visit.
8 December 2022100% built
21 March 202290% built
7 September 202175% built
24 March 202147% built
16 November 202026% built
6 July 202013% built
25 December 201910% built
26 August 20197.5% built
9 January 20194.5% built
11 December 20173.6% built
3 July 20173.6% built
17 January 20173.3% built
9 August 20163.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.