Damac Hills (2) - Mimosa construction photos

69 photos from 9 site inspections, newest first. The percentage is how much of Damac Hills (2) - Mimosa was built on the day of each visit.

23 August 2021100% built

8 February 202199% built

7 April 202097% built

14 October 201965% built

24 April 201938% built

5 December 201815% built

7 August 20184.0% built

11 December 20172.5% built

28 May 20172.1% built

Back to Damac Hills (2) - Mimosa construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.