Damac Hills (2) - Coursetia construction photos

125 photos from 17 site inspections, newest first. The percentage is how much of Damac Hills (2) - Coursetia was built on the day of each visit.

16 March 2022100% built

4 July 202199% built

13 December 202090% built

28 May 202086% built

18 December 201985% built

19 June 201983% built

19 February 201978% built

10 October 201876% built

11 June 201869% built

14 February 201861% built

8 October 201756% built

13 August 201752% built

3 July 201751% built

1 March 201735% built

19 October 201612% built

8 May 20163.8% built

29 March 20153.3% built

Back to Damac Hills (2) - Coursetia construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.