Damac Hills (2) - Claret construction photos
86 photos from 12 site inspections, newest first. The percentage is how much of Damac Hills (2) - Claret was built on the day of each visit.
14 May 2019100% built
20 January 201998% built
9 October 201895% built
11 June 201891% built
14 February 201873% built
8 October 201770% built
13 August 201767% built
3 July 201765% built
17 January 201748% built
9 August 201627% built
10 March 20167.2% built
25 February 20153.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.