Damac Hills (2) - Basswood construction photos
83 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills (2) - Basswood was built on the day of each visit.
21 March 2022100% built
16 June 202199% built
3 February 202199% built
7 April 202096% built
16 October 201970% built
24 April 201940% built
5 December 201818% built
7 August 20185.8% built
9 January 20184.1% built
13 August 20172.7% built
20 March 20172.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.