Damac Hills (2) - Avencia construction photos
54 photos from 8 site inspections, newest first. The percentage is how much of Damac Hills (2) - Avencia was built on the day of each visit.
28 April 2022100% built
24 October 202156% built
19 April 202151% built
16 November 202034% built
7 July 202024% built
9 September 20196.8% built
11 December 20172.2% built
4 July 20171.8% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.