Damac Hills (2) - Aster construction photos

128 photos from 17 site inspections, newest first. The percentage is how much of Damac Hills (2) - Aster was built on the day of each visit.

21 March 2022100% built

26 August 2021100% built

15 March 202199% built

30 November 202095% built

23 March 202090% built

18 December 201987% built

6 May 201985% built

7 November 201883% built

11 June 201874% built

14 February 201862% built

8 October 201760% built

13 August 201758% built

3 July 201756% built

1 March 201733% built

19 October 201611% built

8 May 20163.6% built

29 March 20153.1% built

Back to Damac Hills (2) - Aster construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.