Damac Hills (2) - Aquilegia construction photos
87 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills (2) - Aquilegia was built on the day of each visit.
29 August 2022100% built
26 May 202291% built
21 February 202285% built
30 June 202178% built
13 December 202070% built
7 July 202053% built
23 February 202034% built
14 October 201913% built
12 June 20195.1% built
9 January 20192.4% built
1 March 20182.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.