Damac Hills (2) - Aquilegia construction photos

87 photos from 11 site inspections, newest first. The percentage is how much of Damac Hills (2) - Aquilegia was built on the day of each visit.

29 August 2022100% built

26 May 202291% built

21 February 202285% built

30 June 202178% built

13 December 202070% built

7 July 202053% built

23 February 202034% built

14 October 201913% built

12 June 20195.1% built

9 January 20192.4% built

1 March 20182.1% built

Back to Damac Hills (2) - Aquilegia construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.