Damac Hills (2) - Acuna construction photos

92 photos from 14 site inspections, newest first. The percentage is how much of Damac Hills (2) - Acuna was built on the day of each visit.

21 February 2022100% built

14 July 2021100% built

28 January 202186% built

7 July 202064% built

10 October 201961% built

24 April 201960% built

7 November 201853% built

8 July 201844% built

9 January 201813% built

21 August 20176.0% built

28 May 20175.8% built

11 January 20175.5% built

18 April 20164.0% built

11 August 20152.4% built

Back to Damac Hills (2) - Acuna construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.