Viridian construction photos

59 photos from 8 site inspections, newest first. The percentage is how much of Viridian was built on the day of each visit.

29 July 2025100% built

6 May 202591% built

7 February 202576% built

21 September 202460% built

21 March 202426% built

21 August 20236.3% built

3 May 20234.5% built

13 October 20220% built

Back to Viridian construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.