City Walk Northline 2 construction photos
41 photos from 8 site inspections, newest first. The percentage is how much of City Walk Northline 2 was built on the day of each visit.
4 November 202649% built
19 August 202637% built
18 May 202623% built
24 February 202616% built
3 November 20257.2% built
5 August 20255.2% built
6 May 20255.2% built
26 February 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.