Urban Oasis construction photos

114 photos from 14 site inspections, newest first. The percentage is how much of Urban Oasis was built on the day of each visit.

27 June 2024100% built

5 October 202392% built

29 March 202387% built

24 November 202280% built

18 July 202262% built

17 February 202244% built

20 October 202134% built

17 June 202127% built

8 March 202124% built

17 September 202016% built

3 October 201910% built

5 March 20197.9% built

31 October 20186.7% built

20 June 20183.0% built

Back to Urban Oasis construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.