Reva Residences construction photos

89 photos from 10 site inspections, newest first. The percentage is how much of Reva Residences was built on the day of each visit.

2 June 2022100% built

15 April 202298% built

20 October 202183% built

26 April 202167% built

5 November 202051% built

28 April 202033% built

10 December 201917% built

31 July 20198.6% built

20 December 20185.6% built

12 August 20181.4% built

Back to Reva Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.