Prive By Damac construction photos

160 photos from 17 site inspections, newest first. The percentage is how much of Prive By Damac was built on the day of each visit.

25 September 2019100% built

17 June 201996% built

15 January 201994% built

23 September 201891% built

22 July 201888% built

18 March 201881% built

18 December 201772% built

6 September 201762% built

23 May 201752% built

28 February 201744% built

23 November 201636% built

24 July 201629% built

3 March 201618% built

29 September 201512% built

24 May 201511% built

10 December 20148.8% built

8 April 20142.3% built

Back to Prive By Damac construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.