Prive By Damac construction photos
160 photos from 17 site inspections, newest first. The percentage is how much of Prive By Damac was built on the day of each visit.
25 September 2019100% built
17 June 201996% built
15 January 201994% built
23 September 201891% built
22 July 201888% built
18 March 201881% built
18 December 201772% built
6 September 201762% built
23 May 201752% built
28 February 201744% built
23 November 201636% built
24 July 201629% built
3 March 201618% built
29 September 201512% built
24 May 201511% built
10 December 20148.8% built
8 April 20142.3% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.