Peninsula One construction photos

63 photos from 7 site inspections, newest first. The percentage is how much of Peninsula One was built on the day of each visit.

6 August 2025100% built

21 February 202597% built

18 October 202483% built

9 July 202479% built

15 March 202466% built

26 September 202341% built

6 June 20225.3% built

Back to Peninsula One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.