Jumeirah Living Business Bay construction photos

62 photos from 8 site inspections, newest first. The percentage is how much of Jumeirah Living Business Bay was built on the day of each visit.

16 December 2025100% built

21 August 202591% built

27 March 202573% built

30 October 202450% built

25 June 202425% built

3 January 202414% built

15 August 20239.2% built

9 February 20235.3% built

Back to Jumeirah Living Business Bay construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.