Aykon City 2 construction photos

160 photos from 20 site inspections, newest first. The percentage is how much of Aykon City 2 was built on the day of each visit.

12 October 2023100% built

31 July 202396% built

14 April 202394% built

23 December 202291% built

2 September 202287% built

17 March 202280% built

21 September 202173% built

1 April 202161% built

11 November 202050% built

4 August 202040% built

25 February 202032% built

20 August 201917% built

3 April 201914% built

7 November 201812% built

3 July 201811% built

18 March 20189.1% built

12 November 20176.1% built

13 July 20175.0% built

12 March 20173.1% built

30 October 20162.1% built

Back to Aykon City 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.