Sky Central construction photos

69 photos from 8 site inspections, newest first. The percentage is how much of Sky Central was built on the day of each visit.

28 November 2016100% built

21 August 201693% built

5 October 201570% built

15 June 201555% built

23 March 201543% built

13 November 201423% built

1 July 201415% built

23 February 201415% built

Back to Sky Central construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.