Uniestate Supreme Residence construction photos

56 photos from 6 site inspections, newest first. The percentage is how much of Uniestate Supreme Residence was built on the day of each visit.

19 February 2024100% built

28 August 202370% built

17 April 202364% built

20 December 202246% built

13 September 202231% built

24 March 20224.1% built

Back to Uniestate Supreme Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.