Torino By Oro24 construction photos

93 photos from 9 site inspections, newest first. The percentage is how much of Torino By Oro24 was built on the day of each visit.

14 October 2025100% built

9 May 202598% built

30 September 202471% built

20 March 202443% built

30 November 202337% built

26 September 202326% built

13 June 202316% built

16 February 20235.3% built

1 November 20220.5% built

Back to Torino By Oro24 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.