The Wings construction photos

73 photos from 7 site inspections, newest first. The percentage is how much of The Wings was built on the day of each visit.

26 November 2019100% built

18 March 201971% built

14 November 201850% built

18 September 201841% built

10 July 201833% built

9 April 201822% built

27 December 201711% built

Back to The Wings construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.