112 photos from 14 site inspections, newest first. The percentage is how much of Skyz By Danube was built on the day of each visit.

19 November 2025100% built

28 October 202597% built

28 August 202591% built

30 May 202583% built

24 January 202567% built

13 November 202454% built

20 April 202428% built

28 December 202322% built

31 October 202320% built

26 July 202313% built

1 May 20238.3% built

16 January 20234.8% built

26 September 20220.9% built

18 May 20220.7% built