Resortz Residence construction photos
78 photos from 9 site inspections, newest first. The percentage is how much of Resortz Residence was built on the day of each visit.
3 February 2020100% built
2 October 201995% built
17 June 201981% built
20 March 201963% built
13 December 201847% built
30 August 201833% built
23 May 201820% built
4 February 20186.8% built
17 September 20171.2% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.