Green Diamond 1 construction photos

32 photos from 4 site inspections, newest first. The percentage is how much of Green Diamond 1 was built on the day of each visit.

14 August 2018100% built

10 January 201857% built

21 November 201745% built

7 August 201725% built

Back to Green Diamond 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.