Ar II - Reem Community construction photos
86 photos from 9 site inspections, newest first. The percentage is how much of Ar II - Reem Community was built on the day of each visit.
13 January 2020100% built
30 September 201992% built
27 June 201988% built
25 February 201972% built
6 November 201850% built
22 July 201822% built
11 April 201811% built
19 December 20176.0% built
2 August 20171.5% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.