Arabian Ranches- Azalea Community construction photos
89 photos from 8 site inspections, newest first. The percentage is how much of Arabian Ranches- Azalea Community was built on the day of each visit.
23 July 2019100% built
10 March 201990% built
21 November 201883% built
12 August 201877% built
30 April 201870% built
20 March 201865% built
21 November 201751% built
28 April 20163.5% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.