The Valley - Nima construction photos
41 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of The Valley - Nima was built on the day of each visit.
7 May 202680% built
13 January 202672% built
16 October 202551% built
24 June 202536% built
10 February 202520% built
2 October 20247.0% built
14 May 20241.8% built
8 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.