The Valley - Lillia construction photos

89 photos from 10 site inspections, newest first. The percentage is how much of The Valley - Lillia was built on the day of each visit.

20 July 2026100% built

23 June 202698% built

22 April 202692% built

12 January 202688% built

21 October 202579% built

23 July 202572% built

11 April 202555% built

26 December 202441% built

26 June 20248.4% built

12 March 20242.1% built

Back to The Valley - Lillia construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.