68 photos from 10 site inspections, newest first. The percentage is how much of The Valley - Farm Gardens was built on the day of each visit.

24 March 2026100% built

3 November 202590% built

4 July 202586% built

21 March 202576% built

16 December 202456% built

26 September 202441% built

22 March 202420% built

21 September 20232.5% built

1 June 20230.8% built

11 October 20220% built

Back to The Valley - Farm Gardens construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.