Maysan construction progress
Maysan in Al Yelayiss 2 is 37% built at the Land Department inspection of October 2015. Developer Emaar Bawadi. Completion registered for July 2016.
37%
Built, at the Land Department site inspection of 8 October 2015
123 months past its registered completion date
- Completion date (Land Department)
- July 2016
- Finish at recent pace
- August 2028
- Construction started
- April 2008
- Registered with the Land Department
- September 2013
- Developer
- Emaar Bawadi
- Community
- Al Yelayiss 2
- Units
- 576
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ميسان
- Land Department project number
- 1374
- Land Department site inspections
- 2
Schedule
Maysan was registered to complete in July 2016, 123 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around August 2028.
Site inspections
8 October 2015
37%+9.2 pts
25 November 2013
28%
Context
Emaar Bawadi has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Maysan?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Maysan be completed?
- The completion date registered with the Dubai Land Department is July 2016. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Maysan is built?
- 37%, measured at the Land Department site inspection on 8 October 2015. The Land Department engineers have inspected the site 2 times since November 2013.
- Is Maysan delayed?
- Yes. Its registered completion date of July 2016 has passed and the Land Department still lists it as under construction.
- Who is building Maysan?
- The registered developer is Emaar Bawadi. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Maysan?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.