Maysan construction progress

Maysan in Al Yelayiss 2 was registered to complete in July 2016 and is still under construction. At the last site inspection, in October 2015, it was 37% built. The developer is Emaar Bawadi.

37%

Built, at the site inspection of 8 October 2015

125 months past its registered completion date

Registered completion date
July 2016
Finish at recent pace
August 2028
Construction started
April 2008
First registered
September 2013
Developer
Emaar Bawadi
Community
Al Yelayiss 2
Units
576
Escrow bank
Dubai Islamic Bank
Name in Arabic
ميسان
Project number
1374
Site inspections
2

Schedule

Maysan was registered to complete in July 2016, 125 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around August 2028.

0%25%50%75%100%2009201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2015

37%+9.2 pts

  • Maysan construction site, inspection photo 1, 8 October 2015
  • Maysan construction site, inspection photo 2, 8 October 2015
  • Maysan construction site, inspection photo 3, 8 October 2015
  • Maysan construction site, inspection photo 4, 8 October 2015

25 November 2013

28%

  • Maysan construction site, inspection photo 1, 25 November 2013
  • Maysan construction site, inspection photo 2, 25 November 2013
  • Maysan construction site, inspection photo 3, 25 November 2013
  • Maysan construction site, inspection photo 4, 25 November 2013

All 18 site photos, by inspection date

Context

Emaar Bawadi has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Maysan?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Maysan handover date?
The registered completion date was July 2016, and the register still lists Maysan as under construction. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Maysan?
Maysan was 37% built at the site inspection on 8 October 2015. The site has been inspected 2 times since November 2013. The Land Department took 18 site photos at its inspections.
Is Maysan delayed?
Yes. Its registered completion date of July 2016 has passed and the project is still listed as under construction.
Who is building Maysan?
The registered developer is Emaar Bawadi. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Maysan?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.