Reem - Mira Oasis Community Phase 2 construction photos
131 photos from 14 site inspections, newest first. The percentage is how much of Reem - Mira Oasis Community Phase 2 was built on the day of each visit.
5 September 2019100% built
13 June 201995% built
28 January 201987% built
21 October 201883% built
29 August 201880% built
6 May 201865% built
6 March 201861% built
12 November 201736% built
27 July 201724% built
31 May 201720% built
15 January 201711% built
24 August 20167.8% built
23 December 20157.7% built
19 March 20153.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.