Mohammed Bin Rashid Al Maktoum City- District One, Phase 1 construction photos

125 photos from 17 site inspections, newest first. The percentage is how much of Mohammed Bin Rashid Al Maktoum City- District One, Phase 1 was built on the day of each visit.

24 September 2020100% built

12 March 201995% built

17 April 201890% built

13 February 201888% built

8 November 201787% built

19 July 201785% built

14 May 201780% built

12 January 201775% built

24 October 201666% built

21 August 201661% built

20 July 201660% built

15 June 201655% built

25 April 201650% built

17 February 201639% built

11 November 201528% built

11 August 201518% built

12 February 201510% built

Back to Mohammed Bin Rashid Al Maktoum City- District One, Phase 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.