Damac Lagoons - Lagoon Views 7 construction photos

33 photos from 6 site inspections, newest first. The percentage is how much of Damac Lagoons - Lagoon Views 7 was built on the day of each visit.

17 July 202645% built

25 March 202640% built

7 November 202520% built

1 July 20255.0% built

18 September 20240.6% built

6 February 20240% built

Back to Damac Lagoons - Lagoon Views 7 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.