Damac Lagoons - Lagoon Views 4 construction photos
34 photos from 6 site inspections, newest first. The percentage is how much of Damac Lagoons - Lagoon Views 4 was built on the day of each visit.
17 July 202642% built
25 March 202636% built
5 November 202521% built
1 July 20259.9% built
18 September 20240.4% built
6 February 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.