Damac Lagoons - Lagoon Views 10 construction photos
37 photos from 6 site inspections, newest first. The percentage is how much of Damac Lagoons - Lagoon Views 10 was built on the day of each visit.
1 September 202647% built
14 April 202639% built
9 December 202525% built
24 July 202511% built
10 March 20250.7% built
3 June 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.