Al Khail Heights construction progress
The register lists Al Khail Heights in Al Goze Fourth as complete, with a registered completion date of January 2017. Its last site inspection on record was in April 2018. The developer is Al Khail Heights.
100%
Built, at the site inspection of 25 April 2018
Construction complete
- Registered completion date
- January 2017
- Construction started
- November 2013
- First registered
- May 2014
- Developer
- Al Khail Heights
- Community
- Al Goze Fourth
- Units
- 392
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- الخيل هايتس
- Project number
- 1527
- Site inspections
- 7
Schedule
The register lists Al Khail Heights as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
25 April 2018
100%+4.7 pts
26 September 2017
95%+5.1 pts
27 March 2017
90%+9.1 pts
13 December 2016
81%+15 pts
2 February 2016
67%+7.6 pts
8 October 2015
59%+12 pts
13 November 2014
47%
Own a unit in Al Khail Heights?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Al Khail Heights handover date?
- Construction of Al Khail Heights is recorded as complete, with a registered completion date of January 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Al Khail Heights?
- Al Khail Heights was 100% built at the site inspection on 25 April 2018. The site has been inspected 7 times since November 2014. The Land Department took 71 site photos at its inspections.
- Is Al Khail Heights delayed?
- The register lists construction as complete.
- Who is building Al Khail Heights?
- The registered developer is Al Khail Heights.
- Which bank holds the escrow account for Al Khail Heights?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.