Zazen Ivy construction photos
51 photos from 7 site inspections, newest first. The percentage is how much of Zazen Ivy was built on the day of each visit.
7 May 2026100% built
6 January 202673% built
28 October 202560% built
25 June 202529% built
26 February 202515% built
31 December 202410% built
30 May 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.