Tilal Al Furjan- Phase One construction photos

60 photos from 9 site inspections, newest first. The percentage is how much of Tilal Al Furjan- Phase One was built on the day of each visit.

28 April 2025100% built

24 January 202591% built

25 September 202472% built

16 February 202438% built

17 October 202321% built

27 July 202314% built

29 March 20231.2% built

26 December 20220% built

27 September 20220% built

Back to Tilal Al Furjan- Phase One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.