Pg One At Al Furjan construction photos

69 photos from 9 site inspections, newest first. The percentage is how much of Pg One At Al Furjan was built on the day of each visit.

23 March 2026100% built

26 February 202698% built

5 February 202697% built

3 December 202589% built

31 August 202571% built

20 June 202553% built

23 January 202529% built

10 October 202415% built

6 December 20231.5% built

Back to Pg One At Al Furjan construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.