Pearlz By Danube construction photos

64 photos from 7 site inspections, newest first. The percentage is how much of Pearlz By Danube was built on the day of each visit.

14 May 2024100% built

28 December 202375% built

10 October 202357% built

21 June 202333% built

17 April 202322% built

9 January 20239.3% built

26 September 20220.6% built

Back to Pearlz By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.