Murooj Al Furjan 2 construction photos

59 photos from 7 site inspections, newest first. The percentage is how much of Murooj Al Furjan 2 was built on the day of each visit.

15 February 2024100% built

17 October 202385% built

27 July 202378% built

15 March 202357% built

5 December 202238% built

5 September 202213% built

20 April 20222.0% built

Back to Murooj Al Furjan 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.